allinhyperscale.com / Guides / Campus planning
Guide · Engineering

How to plan a hyperscale campus: land, power and phases

A campus plan answers three questions: how many megawatts the land can hold, how many the grid will deliver, and when. This guide shows the method behind the campus planner and works it through a 120-hectare site with a 900 MW grid offer.

Updated October 20268 min readBy Ziya DemirData center project directorFounder of allindatacenter.com

In short

  • Land capacity = site area × building cover × storeys × IT kW per m², which rises with rack density.
  • Grid capacity for IT = grid import ÷ PUE.
  • The smaller of the two is the campus; on most sites it is the grid.
  • 120 ha, two storeys, 40 kW racks and 900 MW of grid give 720 MW IT in 5 buildings and 3 phases, fully live after about 54 months.
Step 1

How many megawatts the land can hold

Land capacity
ITland = A × cover × storeys × d
A site area (m²), cover share under buildings, d IT kW per m² of gross building area
Rack densityIT per m² of building
8 kW0.8 kW/m²
15 kW · cloud1.1 kW/m²
30 kW1.7 kW/m²
40 kW · mixed2.0 kW/m²
60 kW2.6 kW/m²
130 kW · AI, liquid3.8 kW/m²

The curve is a planning fit to published campuses; it includes electrical and mechanical rooms inside the building, not yards.

Step 2

How many the grid will deliver

The grid import covers IT and everything else, so the IT it supports is grid ÷ PUE. A 900 MW offer at PUE 1.25 supports 720 MW of IT. Compare it with the land capacity: the lower number is the campus, and it tells you which side to work on.

Step 3

Buildings

Divide campus IT by the IT per building and round up. Cloud designs often use 30–100 MW buildings; AI campuses 150 MW or more. Larger buildings save land and duplicated plant but put more capacity behind one energisation date.

Step 4

Phasing to the substation

Group buildings into phases that match transformer bays and grid capacity. The first phase goes live after the lead time to first power, typically 24–36 months; each further phase follows at a steady step, often 12 months. Full build-out = lead + (phases − 1) × step.

Step 5

Energy, water, transformers and cost

  • Facility power = IT × PUE.
  • Energy per year = IT × average load × PUE × 8,760 h.
  • Water per year = IT × average load × 8,760 h × WUE (litres per kWh).
  • HV transformers (100 MVA, N+1) = facility power ÷ 90 MW, rounded up, plus one.
  • Build cost = IT × cost per MW; $11.3M is the 2026 average, excluding IT.
Worked example

120 ha, 900 MW grid, 40 kW racks

QuantityValue
Footprint = 120 ha × 25 %300,000 m²
Building area, two storeys600,000 m²
Land allows = 600,000 × 2.0 kW/m²1,200 MW IT
Grid allows = 900 ÷ 1.25720 MW IT · grid binds
Buildings of 150 MW · phases of 25 buildings · 3 phases
First power · full build-out (30 + 2 × 12)30 · 54 months
Energy at 80 % load≈ 6,300 GWh/yr
Water at WUE 0.3 L/kWh≈ 1.5 million m³/yr
Racks at 40 kW · HV transformers18,000 · 11
Build cost at $11.3M per MW≈ $8.1 billion

The site could hold 1,200 MW, but the grid offer caps it at 720 MW, or 6 MW per hectare, above the 3.5–5 MW typical of published single- and mixed-storey campuses because of the second storey.

Plan your own campusChange hectares, storeys, density, grid, building size and phasing.
Open the planner →
Levers

What moves the answer

  • Grid binds: negotiate more capacity or an earlier date, lower PUE, or add on-site generation for early phases.
  • Land binds: add a storey, raise rack density, or reduce setbacks and yard space.
  • Time binds: energise smaller first phases, use bridging power, prefabricate (see allinMODULAR).
Questions

Questions about campus planning

How many MW per hectare should I assume?

3.5–5 MW per hectare for published campuses as a first figure; more with multiple storeys and high-density AI racks, less with large buffers.

How big should each building be?

Large enough to keep plant efficient, small enough to energise in step with the grid. Cloud campuses often use 30–100 MW; AI campuses 150 MW or more.

How many transformers does a campus need?

At 100 MVA each with N+1, roughly one per 90 MW of facility power plus a spare: 11 for a 900 MW campus.

Does build cost include servers?

No. The $11.3M per MW average covers the building, power and cooling. IT equipment comes on top and usually costs more.

Sources

Sources

  • Planner model on this site; IT density curve fitted to published campuses.
  • JLL 2026 average build cost; liquid cooling adder $1–2M per MW.
  • Worked figures are screening values, not a design.